{"id":38320,"date":"2018-08-23T23:42:57","date_gmt":"2018-08-23T15:42:57","guid":{"rendered":"https:\/\/wp-productionenv-bjg9h2g2bgg5b8aa.southeastasia-01.azurewebsites.net\/news\/boeing-nasa-managing-sls-core-stage-hardware-traffic-ahead-of-first-vehicle-stacking\/"},"modified":"2018-08-23T23:42:57","modified_gmt":"2018-08-23T15:42:57","slug":"boeing-nasa-managing-sls-core-stage-hardware-traffic-ahead-of-first-vehicle-stacking","status":"publish","type":"post","link":"https:\/\/starpath.global\/news\/boeing-nasa-managing-sls-core-stage-hardware-traffic-ahead-of-first-vehicle-stacking\/","title":{"rendered":"Boeing, NASA managing SLS Core Stage hardware traffic ahead of first vehicle stacking"},"content":{"rendered":"<p>A traffic jam of NASA Space Launch System (SLS) Core Stage hardware that needs to be assembled is building at NASA\u2019s Michoud Assembly Building (MAF) in New Orleans. Completed subsections of the first vehicle and structural test articles (STA) are lining up to be put together at the same time as structures for the second vehicle are ready to begin welding in the same area.\n<\/p>\n<p>Prime contractor Boeing is working with NASA to get the right pieces through the plant in the best sequence possible. A lot of first-time work remains for the first vehicle and test hardware, so Boeing and NASA are shuffling tanks and re-sequencing work schedules while finishing with configuring other buildings and readying the facility for long-term stage production.<\/p>\n<p>Four stacks for two stacking cells<\/p>\n<p>While the engine section continues to pace delivery of the first flight stage, Boeing and NASA are also working to optimize work schedules for other parts of Core Stage-1 (CS-1) and test hardware that will support the first SLS launch on Exploration Mission-1 (EM-1), forecast now in mid-2020. Currently, the top half of CS-1 and the liquid hydrogen (LH2) STA are finishing work leading up to their assembly.<\/p>\n<p>Even without its engines installed, Core Stages will stretch to around 200 feet in length. That\u2019s too long to stack everything vertically in one place at MAF, so the five main pieces (the forward skirt, the liquid oxygen tank, the intertank, the liquid hydrogen tank, and the engine section) will be assembled into two half-stages first before the whole stage is finally connected while horizontal.<\/p>\n<p>Along with the two half stages that need to be stacked to help complete the stage, the two remaining STAs (for the liquid hydrogen and liquid oxygen tanks) must be completed and shipped to their test stands at the Marshall Space Flight Center (MSFC) in Huntsville, Alabama. The current plan is to assemble the \u201cforward join\u201d of the CS-1 forward skirt, liquid oxygen (LOX) tank, and intertank first.&nbsp; Stacking the LH2 STA, which will connect the&nbsp;LH2 qualification tank with two simulators on other end, would follow shortly behind that.<\/p>\n<p><img fetchpriority=\"high\" decoding=\"async\" aria-describedby=\"caption-attachment-57738\" class=\"wp-image-57738 size-full\" src=\"https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20170718_p_4_tanks_in_110_-14.crop_.35pct.jpg\" alt=\"\" width=\"1564\" height=\"1194\" srcset=\"https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20170718_p_4_tanks_in_110_-14.crop_.35pct.jpg 1564w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20170718_p_4_tanks_in_110_-14.crop_.35pct-350x267.jpg 350w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20170718_p_4_tanks_in_110_-14.crop_.35pct-458x350.jpg 458w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20170718_p_4_tanks_in_110_-14.crop_.35pct-768x586.jpg 768w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20170718_p_4_tanks_in_110_-14.crop_.35pct-1170x893.jpg 1170w\" sizes=\"(max-width: 1564px) 100vw, 1564px\"><\/p>\n<p id=\"caption-attachment-57738\" class=\"wp-caption-text\">Bare metal propellant tanks fill the aisleway and processing cells in the Building 110 VAB at MAF, July 2017. A similar convergence of hardware could occur this Fall. From left to right, Cells A and D at the bottom will be used for upcoming \u201cmajor joins\u201d of the first Core Stage. The aisleway blocked by the long hydrogen tank in the middle here will be needed for access to those two cells and the VAC welding tool (upper left). Credit: NASA\/Jude Guidry.<\/p>\n<p>NASA and Boeing have two cells configured for vertical stacking\/integration in Building 110. Cell A was originally configured for vertical stacking when Building 110 was initially constructed over 50 years ago; it has platforms at fixed levels. Cell D was converted into an integration cell for SLS, and has a single, movable platform that can provide access up and down the cell.<\/p>\n<p>The LH2 tank itself is over 130 feet long; while the tank can and does fit in Cell D by itself, there\u2019s not enough clearance to get it out of the cell with anything else attached and possibly not even enough room to fit either of the simulators in the cell with the tank. An LH2 tank is also so large that it will block access to Cell A and Cell D for other hardware elements.<\/p>\n<p>Aerospace &amp; Defense<path d=\"M7.59009 18.59L9.00009 20L17.0001 12L9.00009 4L7.59009 5.41L14.1701 12\" style=\"animation: initial !important; background: initial !important; border: 0px !important; box-shadow: none !important; color: inherit !important; cursor: inherit !important; direction: inherit !important; display: inline !important; fill: currentcolor !important; filter: initial !important; float: none !important; margin: 0px !important; opacity: initial !important; outline: 0px !important; overflow: initial !important; padding: 0px !important; stroke: initial !important; transform: initial !important; vertical-align: initial !important; visibility: inherit !important;\"><\/path>Spaceflight history books<path d=\"M7.59009 18.59L9.00009 20L17.0001 12L9.00009 4L7.59009 5.41L14.1701 12\" style=\"animation: initial !important; background: initial !important; border: 0px !important; box-shadow: none !important; color: inherit !important; cursor: inherit !important; direction: inherit !important; display: inline !important; fill: currentcolor !important; filter: initial !important; float: none !important; margin: 0px !important; opacity: initial !important; outline: 0px !important; overflow: initial !important; padding: 0px !important; stroke: initial !important; transform: initial !important; vertical-align: initial !important; visibility: inherit !important;\"><\/path>Spaceflight news subscription<path d=\"M7.59009 18.59L9.00009 20L17.0001 12L9.00009 4L7.59009 5.41L14.1701 12\" style=\"animation: initial !important; background: initial !important; border: 0px !important; box-shadow: none !important; color: inherit !important; cursor: inherit !important; direction: inherit !important; display: inline !important; fill: currentcolor !important; filter: initial !important; float: none !important; margin: 0px !important; opacity: initial !important; outline: 0px !important; overflow: initial !important; padding: 0px !important; stroke: initial !important; transform: initial !important; vertical-align: initial !important; visibility: inherit !important;\"><\/path>\n<p>     (adsbygoogle = window.adsbygoogle || []).push({});<\/p>\n<p>\u201cOne of the challenges we have is managing traffic in the aisle way of Building 110, because stacking the qual articles \u2014 LH2 first, then followed by LOX \u2014 all those things consume the aisle space as we\u2019re staging,\u201d Steven Ernst, Boeing\u2019s Core Stage Engineering Support Manager, said during a July interview with NASASpaceflight.com.<\/p>\n<\/p>\n<h4 class=\"widget-title penci-border-arrow\">See Also<\/h4>\n<ul>\n<li>SLS Forum Section<\/li>\n<li>L2 SLS Section<\/li>\n<li>Click here to Join L2<\/li>\n<\/ul>\n<p>\u201cSo it\u2019s a bit of a dance, and getting the qual articles out of here and on their way to Marshall is a priority, so when can get through all of the testing and all of the data analysis and get through design certification review.\u201d Simultaneously, getting the first vehicle completed is also a priority \u2014 it\u2019s in the critical path for the EM-1 launch.<\/p>\n<p>Schedules change frequently as the workforce progresses through the first-time learning curve&nbsp;and Boeing is constantly monitoring work developments on the different assemblies to see when each of them becomes ready. \u201cThe reason it\u2019s fluid and we do it on purpose [is because] it\u2019s first-time operations,\u201d Rick Navarro, Boeing\u2019s Director of Space and Launch Operations, explained.<\/p>\n<p>\u201cWe have two or three competing articles; let\u2019s say one gets through with no issues but one develops a concern that we have to address, then all of a sudden it makes more sense to do one ahead of the other.\u201d<\/p>\n<p>Forward skirt ready and waiting to stack<\/p>\n<p>The least complex of the five major stage elements, the CS-1 forward skirt is ready for that next step. \u201cIt\u2019s essentially as far as it can go as an end item by itself,\u201d Navarro said. \u201cThe next thing practically that you can do with it is mate it to the rest of the stack.\u201d<\/p>\n<p>Navarro outlined the overall work done to reach the milestone: \u201cFirst obviously [was] the structural build, the insulation, the components were installed, the flight computers,\u201d he explained. \u201cThe wire harnesses were tested individually first, then connected to the flight computer and other avionics, and they just finished the suite of testing as a total forward skirt.\u201d<\/p>\n<p>The review of all the testing was completed just prior to speaking with Navarro in early July. \u201cThe review [was] called break of configuration, where you go over all the test findings and make sure you understood it all and it\u2019s all explained and dispositioned, and we had the official word to break the test configuration last night, so we\u2019re done,\u201d he noted at the time.<\/p>\n<p><img loading=\"lazy\" decoding=\"async\" aria-describedby=\"caption-attachment-57739\" class=\"wp-image-57739 size-full\" src=\"https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20180727_forwardskitupdate-007_0.20pct.jpg\" alt=\"\" width=\"1591\" height=\"1061\" srcset=\"https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20180727_forwardskitupdate-007_0.20pct.jpg 1591w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20180727_forwardskitupdate-007_0.20pct-350x233.jpg 350w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20180727_forwardskitupdate-007_0.20pct-525x350.jpg 525w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20180727_forwardskitupdate-007_0.20pct-768x512.jpg 768w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20180727_forwardskitupdate-007_0.20pct-1170x780.jpg 1170w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20180727_forwardskitupdate-007_0.20pct-585x390.jpg 585w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/maf_20180727_forwardskitupdate-007_0.20pct-263x175.jpg 263w\" sizes=\"(max-width: 1591px) 100vw, 1591px\"><\/p>\n<p id=\"caption-attachment-57739\" class=\"wp-caption-text\">CS-1 forward skirt standalone work is complete at MAF, July 2018. First completed, the ring will be the last of the three pieces added to the \u201cforward join.\u201d Credit: NASA\/Eric Bordelon.<\/p>\n<p>The first to reach that point, it will be the last to be stacked, going on top of the LOX tank at the end of sequence.<\/p>\n<p>\u201cThere are some things that purposely have to be delayed until you\u2019re stacked or nearly stacked,\u201d Navarro said. \u201cThere\u2019s some insulation cutouts that you wouldn\u2019t insulate until you get to stack. There\u2019s some connections, there\u2019s some protective covers, those type of things. That\u2019s all minor stuff to prepare it for the stack.\u201d<\/p>\n<p>Following functional testing, four checkerboard photogrammetry targets were added around the circumference.<\/p>\n<p>Intertank functional testing nearing completion<\/p>\n<p>The CS-1 intertank is one step behind the forward skirt. The element is fully outfitted with its own systems and began its own subassembly-level functional testing in mid-July to verify everything inside is connected and operating properly. One of the last major pre-test steps was to install the flight avionics boxes into the intertank.<\/p>\n<p>\u201cFirst, we laid out all the [wire] harnesses, [and] tested [them] individually inside the intertank,\u201d Navarro explained. \u201cFor that, we had to get all the harnesses routed correctly\u2026through the entire volume. To make sure that we did that right, we had 3-D printed avionics boxes [installed] just to get everything right.\u201d<\/p>\n<p>\u201cAfter we tested the harnesses individually, then we removed the placeholder 3-D printed boxes and put the actual avionics boxes [in],\u201d he added.<\/p>\n<p>For the functional testing, the Boeing team is running some of their test cables through systems tunnel connectors to plug into the network of components inside the intertank. Full-up, end-to-end systems checkout will occur later after the systems tunnel itself is attached to the whole stage in the Final Assembly area.<\/p>\n<p>\u201cThere are no prescribed mechanical tests, other than some leak checks on installed tubing runs, so obviously we have to clear leak checks on those,\u201d Navarro noted. \u201cThe rest is electrical.\u201d<\/p>\n<p>Navarro also noted that the additional development flight instrumentation (DFI) on the first vehicle adds to the length of the checkout. \u201cA significant part of the testing is all the sensors [and] first time flight instrumentation,\u201d he said.<\/p>\n<p><img loading=\"lazy\" decoding=\"async\" aria-describedby=\"caption-attachment-57742\" class=\"wp-image-57742 size-full\" src=\"https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/P1100873.35pct.jpg\" alt=\"\" width=\"1714\" height=\"1286\" srcset=\"https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/P1100873.35pct.jpg 1714w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/P1100873.35pct-350x263.jpg 350w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/P1100873.35pct-466x350.jpg 466w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/P1100873.35pct-768x576.jpg 768w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/P1100873.35pct-1170x878.jpg 1170w\" sizes=\"(max-width: 1714px) 100vw, 1714px\"><\/p>\n<p id=\"caption-attachment-57742\" class=\"wp-caption-text\">-Z side of the CS-1 intertank at MAF, August 13. Credit: Philip Sloss for NSF\/L2.<\/p>\n<p>\u201cThey\u2019ve been individually calibrated and tested but now it is stimulating those sensors, whether it\u2019s an accelerometer or a temperature probe, stimulating it and getting the right response.\u201d<\/p>\n<p>Last week Ernst noted that testing has gone well, with a few issues remaining to work through. \u201cWe have been in the midst of some sensor troubleshooting, which has slowed progress. The original plan was to break the [test] config earlier in the month. [Now] it\u2019s looking like in the next week and a half to two [weeks], again driven by troubleshooting of sensors and things. In the main the progress is exceptional.\u201d<\/p>\n<p>Once they are given the \u2018go\u2019 to disconnect all the test cabling, the intertank will be closed out to be taken into Cell D next month for final pre-stacking steps ahead of bringing the LOX tank in and connecting it to the top of the intertank.<\/p>\n<p>LOX tank outfitting<\/p>\n<p>In parallel with the intertank functional testing, technicians are going through the pre-stacking steps for the LOX tank. Primary spray-on foam insulation (SOFI) work on the CS-1 LOX tank in Cell N was completed in June and the tank was moved back to Area 6 in the main building at MAF, Building 103.<\/p>\n<p><img loading=\"lazy\" decoding=\"async\" aria-describedby=\"caption-attachment-57743\" class=\"wp-image-57743 size-full\" src=\"https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/P1100764.35pct.jpg\" alt=\"\" width=\"1714\" height=\"1286\" srcset=\"https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/P1100764.35pct.jpg 1714w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/P1100764.35pct-350x263.jpg 350w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/P1100764.35pct-466x350.jpg 466w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/P1100764.35pct-768x576.jpg 768w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/P1100764.35pct-1170x878.jpg 1170w\" sizes=\"(max-width: 1714px) 100vw, 1714px\"><\/p>\n<p id=\"caption-attachment-57743\" class=\"wp-caption-text\">CS-1 LOX tank in Cell A at MAF, August 13. From a \u201cLOX bridge\u201d platform\/clean room set up at the top of the tank, two technicians are to be winched down through the forward manhole to the bottom to torque one series of fasteners inside the aft dome while others are tightened on the outside. Credit: Philip Sloss for NSF\/L2.<\/p>\n<p>A series of small, circular sensor islands were masked off prior to foam sprays to allow for later access; in Area 6, the development flight instrumentation (DFI) sensors themselves were added to the islands and connected to their wiring runs. The sensor islands are similar to \u201cDFI islands\u201d flown on the first six Shuttle External Tanks.<\/p>\n<p>The earlier plan was to completely finish testing and checkout of the sensor islands, install an internal sensor mast, and then put the LOX tank into Cell A for installation of the LOX tank sump; however, delivery of the sensor mast was delayed, which prompted Boeing to bring the sump install forward.<\/p>\n<p>\u201cWe talked about [how] it\u2019s always a dance and it\u2019s always a balance,\u201d Ernst said on August 15. \u201cThe sensor mast, which goes inside the tank and includes all the depletion sensors and propellant level sensors [and] there\u2019s some thermal sensors on there, we had a procurement issue with the wire. It\u2019s delayed the sensor mast, so we decided to re-sequence [the LOX tank work].\u201d<\/p>\n<p>Moved up ahead of the internal sensor mast installation, the sump install is now set to take place this week. \u201cThat\u2019s a bit of tricky installation,\u201d Ernst noted. \u201cWe actually have to lower somebody inside the tank to do a ring of internal fasteners as well as external fasteners.\u201d<\/p>\n<p>The salad-bowl shaped sump cover fits outside the outer mold line of the tank\u2019s aft dome, but the inside of the tanks have to be kept clean and environmentally controlled, so the technicians going into the tank will have to do their work while suspended.<\/p>\n<p><img loading=\"lazy\" decoding=\"async\" aria-describedby=\"caption-attachment-57744\" class=\"wp-image-57744 size-full\" src=\"https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/STS-1-Rollout.DFI-Islands.jpg\" alt=\"\" width=\"1384\" height=\"882\" srcset=\"https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/STS-1-Rollout.DFI-Islands.jpg 1384w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/STS-1-Rollout.DFI-Islands-350x223.jpg 350w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/STS-1-Rollout.DFI-Islands-549x350.jpg 549w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/STS-1-Rollout.DFI-Islands-768x489.jpg 768w, https:\/\/www.nasaspaceflight.com\/wp-content\/uploads\/2018\/08\/STS-1-Rollout.DFI-Islands-1170x746.jpg 1170w\" sizes=\"(max-width: 1384px) 100vw, 1384px\"><\/p>\n<p id=\"caption-attachment-57744\" class=\"wp-caption-text\">Circular DFI islands can be seen on the top of the External Tank for the STS-1 Space Shuttle vehicle in two images taken during its rollout to the pad on December 29, 1980. The first SLS Core Stage will have similar sensor islands on both its cryogenic propellant tanks. Credit: NASA.<\/p>\n<p>A clean room was installed over the top end of the tank after it was loaded in Cell A. \u201cThe LOX bridge [is what] we call it,\u201d Ernst explained. \u201cThat will be sealed against the forward opening in the tank. We have a clean room that\u2019s an integral part of that and then we literally will lower the quality [inspector] and the technician down through that forward manhole to the bottom of the tank.\u201d<\/p>\n<p>After the sump is installed, the tank will return to Area 6 to install the sensor mast and finish up remaining sensor closeouts. \u201cWe can\u2019t do it in the vertical, we don\u2019t have the access to do the sensor mast, so we\u2019ll come out [of Cell A], break over [to horizontal], go back to Area 6, get the clean room entry [set up], get the sensor mast installed and some other minor work we\u2019ll do other there and then we\u2019ll be waiting to come back here to Cell D to stack on top of the intertank,\u201d Ernst said.<\/p>\n<p class=\"post-nav-links\">Pages: 1 2<\/p>\n","protected":false},"excerpt":{"rendered":"<p>A traffic jam of NASA Space Launch System (SLS) Core Stage hardware that needs to be assembled is building at NASA\u2019s Michoud Assembly Building (MAF) in New Orleans. Completed subsections of the first vehicle and structural test articles (STA) are lining up to be put together at the same time as structures for the second [&hellip;]<\/p>\n","protected":false},"author":1,"featured_media":0,"comment_status":"","ping_status":"","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"inline_featured_image":false,"footnotes":"","_links_to":"","_links_to_target":""},"categories":[2],"tags":[8961,8949,3718,4011,7866,624],"class_list":["post-38320","post","type-post","status-publish","format-standard","hentry","category-news","tag-cs-1","tag-cs-2","tag-em-1","tag-em-2","tag-maf","tag-sls"],"acf":[],"_links":{"self":[{"href":"https:\/\/starpath.global\/blog\/wp-json\/wp\/v2\/posts\/38320"}],"collection":[{"href":"https:\/\/starpath.global\/blog\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/starpath.global\/blog\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/starpath.global\/blog\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/starpath.global\/blog\/wp-json\/wp\/v2\/comments?post=38320"}],"version-history":[{"count":0,"href":"https:\/\/starpath.global\/blog\/wp-json\/wp\/v2\/posts\/38320\/revisions"}],"wp:attachment":[{"href":"https:\/\/starpath.global\/blog\/wp-json\/wp\/v2\/media?parent=38320"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/starpath.global\/blog\/wp-json\/wp\/v2\/categories?post=38320"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/starpath.global\/blog\/wp-json\/wp\/v2\/tags?post=38320"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}