First SLS LVSA ready for Artemis 1, second in production
The interstage connector for the first NASA Space Launch System (SLS) vehicle was delivered to NASA in mid-July and is in transit to its launch site. The Launch Vehicle Stage Adapter (LVSA) was completed by Teledyne Brown Engineering at the Marshall Space Flight Center (MSFC) in Alabama and officially turned over to the agency for…
-

EGS, Jacobs begin SLS booster build up for Artemis 1
NASA Exploration Ground Systems and prime test and operations contractor Jacobs mated the first of two Space Launch System (SLS) aft motor segments for the Artemis 1 launch with its aft skirt on June 24. The connection of two of the major elements of the right-hand aft booster assembly continues preparations of Northrop Grumman booster…
-

Boeing powers up first SLS Core Stage for Green Run system checkouts
Boeing powered up the Core Stage for the first Space Launch System on the B-2 Test Stand at the NASA’s Stennis Space Center in Mississippi last week following a long stand down due to the coronavirus pandemic. The first Core Stage is at the outdoor facility for a Green Run test campaign that culminates in…
-

SLS booster segments arrive in Florida, but stacking on hold until core stage test
The 10 booster segments for the first flight of NASA’s Space Launch System travel across a bridge between Titusville, Florida, and the Kennedy Space Center on Monday, June 15. Credit: Northrop Grumman Fueled segments of the solid rocket boosters that will lift off on the first flight of NASA’s Space Launch System have arrived at…
-

EGS begins Artemis 1 launch processing of SLS Booster hardware
NASA’s Exploration Ground Systems (EGS) program is stepping into the launch processing flow for the Artemis 1 mission after taking delivery of Solid Rocket Booster (SRB) hardware for the Space Launch System (SLS) rocket that will start the uncrewed lunar orbit mission next year. SLS Booster prime contractor Northrop Grumman turned over almost all of…
-

EGS begins Artemis 1 launch processing of SLS Booster hardware
NASA’s Exploration Ground Systems (EGS) program is stepping into the launch processing flow for the Artemis 1 mission after taking delivery of Solid Rocket Booster (SRB) hardware for the Space Launch System (SLS) rocket that will start the uncrewed lunar orbit mission next year. SLS Booster prime contractor Northrop Grumman turned over almost all of…
-

Stennis returning as battle to protect SLS maiden launch in 2021 restarts
Hands-on operations with the Space Launch System (SLS) resumed this week, following a lengthy standdown due to the restrictions relating to COVID-19. This included a return to Green Run preparations at the Stennis Space Center, with “limited crews” preparing the Artemis-1 core stage on the B-2 test stand for what will be one of the…
-

Hopeful for launch next year, NASA aims to resume SLS operations within weeks
A crane hoisted the Space Launch System core stage into the B-2 test stand at NASA’s Stennis Space Center in January. Credit: NASA/SSC With the Space Launch System’s inaugural test flight now officially delayed to November 2021, NASA says work halted by the coronavirus pandemic will resume within weeks to prepare for the first test-firing…
-

Prior to workplace closures, SLS was making good progress ahead of opening missions
Prior to the shut down of work last month in response to the coronavirus disease 2019 (COVID-19) pandemic, NASA’s Space Launch System (SLS) Program was working towards milestones for its first two launches. At Stennis Space Center in Mississippi, Core Stage prime contractor Boeing was getting ready to do powered checkouts of the first flight…
-

SLS at Home: Program and Contractors adjusting to telework
With key worksites closed and activity suspended to protect their workforce from the 2019 novel coronavirus disease (COVID-19), NASA’s Space Launch System (SLS) Program is working on what it can from home. The program’s headquarters at the Marshall Space Flight Center (MSFC) in Huntsville, Alabama, are closed in response to the uncontained virus outbreak. The…