Artemis 1 SLS stacking work running long, preps for integrated tests continue in parallel
Final securing of the Space Launch System (SLS) Launch Vehicle Stage Adapter (LVSA) to the Core Stage for Artemis 1 in the Vehicle Assembly Building (VAB) at the Kennedy Space Center (KSC) in Florida was slowed down by issues discovered when workers started bolting the two elements together. NASA’s Exploration Ground Systems (EGS) and prime…
-

NASA SLS core/booster mate sets the stage for Artemis 1 pre-launch checkout
The integrated operations team of NASA’s Exploration Ground Systems (EGS) and prime launch processing contractor Jacobs completed mating the SLS Core Stage for Artemis 1 with its boosters on June 13, another in a series of firsts that will culminate in the debut flight of NASA’s new launch vehicle, currently projected for no earlier than…
-

EGS starts Artemis 1 SLS Core Stage lift
After a month of thermal protection system foam repairs and other preparations, workers with NASA’s Exploration Ground Systems (EGS) and prime test operations and support contractor Jacobs at the Kennedy Space Center in Florida started lift operations on the Space Launch System (SLS) Core Stage for Artemis 1 in the Vehicle Assembly Building (VAB) on…
-

NASA evaluating schedule, launch date forecasts for Artemis 2
NASA is currently forecasting that Artemis 2 will be ready to launch no earlier than (NET) September 2023, but similar to attempting to forecast when Artemis 1 will be ready to launch, there is also uncertainty in when Artemis 2 might fly. The second joint test flight of NASA’s Orion and Space Launch System (SLS)…
-

Senators spar over the idea of giving billions to Jeff Bezos’ Blue Origin venture for lunar lander program
An artist’s conception shows the human landing system that’s being developed by Blue Origin and its industry partners in the foreground, and Blue Origin’s Blue Moon cargo lander in the far background. (Blue Origin Illustration) The tussle over NASA funding for lunar landing systems has touched down in the Senate — with one leading senator…
-

SLS Core Stage thermal protection system refurbishment in work at Kennedy for Artemis 1
NASA’s Space Launch System (SLS) and Exploration Ground Systems (EGS) programs are working with Core Stage prime contractor Boeing and prime test operations and support contractor Jacobs to finish repairs to thermal protection system (TPS) spray-on foam insulation on the Artemis 1 Core Stage at the Kennedy Space Center in Florida. The TPS foam, cork,…
-

Nelson cites China’s growing space prowess, calls for sustained NASA funding
STORY WRITTEN FOR CBS NEWS & USED WITH PERMISSION NASA Administrator Bill Nelson holds up a picture of China’s Zhurong Mars rover during a virtual hearing with a House of Representatives subcommittee Wednesday. Credit: NASA/U.S. House of Representatives Holding up a photo taken by China’s new Mars lander, NASA Administrator Bill Nelson warned Congress Wednesday that his…
-

SLS Core Stage Green Run validates propulsion system performance and modeling
Engineers with NASA’s Space Launch System (SLS) program and prime Core Stage contractor Boeing continue to review terabytes of data from the now-complete, once-in-a-generation Green Run design verification test campaign. A series of eight test cases were completed, culminating in a 500-second long, full-duration static firing of the stage in the B-2 Test Stand at…
-

NASA EGS, Jacobs preparing SLS Core Stage for Artemis 1 stacking
The Core Stage of NASA’s first Space Launch System (SLS) vehicle arrived at the Kennedy Space Center (KSC) and was moved into the Vehicle Assembly Building (VAB) on April 29. The stage is now in the hands of KSC’s Exploration Ground System (EGS) program and prime test operations and support contractor (TOSC) Jacobs. The long-awaited…
-

Ten month schedule to ready SLS for Artemis 1 launch after Core Stage arrives at KSC
NASA’s Exploration Ground Systems (EGS) program is looking at a wide range of forecasts for when they can complete testing necessary to be ready to launch Artemis 1. The Core Stage of NASA’s first Space Launch System (SLS) vehicle arrived at the Kennedy Space Center and was moved into the Vehicle Assembly Building (VAB) on…