Pad 39B in the final stages in preparation to welcome SLS Mobile Launcher
The final work on Kennedy Space Center’s Pad 39B is being conducted in line with the construction and outfitting of systems on the Mobile Launcher (ML) for the Space Launch System (SLS). This multi-element verification and validation (V&V) testing is set to take place next year, a full dress rehearsal ahead of the rollout of…
-

Preparing the Mobile Launcher to be armed and ready for SLS
The Ground Systems Development and Operations (GSDO) team at the Kennedy Space Center (KSC) in Florida is continuing construction and testing to get ready to support upcoming Exploration Mission launches. Testing at the Launch Equipment Test Facility (LETF) is in full swing delivering launch vehicle umbilicals and swing arms to the Mobile Launcher (ML). LEFT…
-

SLS Upper Stage arrives at the Cape as the LETF tests its umbilicals
A major milestone in the build-up to the maiden launch of the Space Launch System has seen the arrival of the Interim Cryogenic Propulsion Stage (ICPS) at Cape Canaveral. Meanwhile, tests are continuing on the umbilicals that will feed this Upper Stage, ahead of joining forces when mated on the Mobile Launcher. ICPS: The upper stage…
-

KSC evaluating the groundwork challenges for SLS Block 1B upgrades
NASA’s monster rocket will evolve into an even larger vehicle early in her lifetime, as the Block 1 rocket grows into the workhorse known as the Block 1B. With a large increase in capability – and height – the Block 1B will require a revamp of numerous elements of the KSC ground systems, ranging from…
-

SLS ML revamp after EM-1 included Europa mission considerations
With work continuing on a lengthy project to convert the Mobile Launcher (ML) for use with the Space Launch System (SLS), a NASA manager has spoken about the challenges of preparing the huge structure for the rocket’s undefined manifest. The hope of SLS involvement with a mission to Europa included considerations for a second ML.…
-

SLS Tail Service Masts undergoing construction ahead of LETF testing
Engineers have begun the construction of two huge Tail Service Masts that will play a crucial role with the Space Launch System (SLS) on launch day. The TSMUs (Tail Service Mast Umbilicals) will be tested on the Vehicle Motion Simulator (VMS) at the Kennedy Space Center, before being installed on the deck of the Mobile Launcher…
-

SLS Tail Service Masts undergoing construction ahead of LETF testing
Engineers have begun the construction of two huge Tail Service Masts that will play a crucial role with the Space Launch System (SLS) on launch day. The TSMUs (Tail Service Mast Umbilicals) will be tested on the Vehicle Motion Simulator (VMS) at the Kennedy Space Center, before being installed on the deck of the Mobile Launcher…
-

KSC testing the VS – designed to dampen SLS swaying on a windy pad
Engineers at the Kennedy Space Center are set to test the Vehicle Stabilizer (VS) via a motion simulator at the Launch Equipment Test Facility (LETF). The VS will have a key role during Space Launch System (SLS) pad flows, dampening out the loads on the huge structure as the monster rocket “sways” in the often-windy conditions…
-

Super Crawler CT-2 test run marks 50th anniversary
NASA’s Crawler Transporter -2 (CT-2) is continuing to enjoy its first outing in over a year, as its roll to Pad 39B tests its latest modifications ahead of an active role with the Space Launch System (SLS). Its trip at the pad began last week, but was staggered to mark the 50th anniversary of the…
-

KSC continuing its spaceport transition for the new era
It’s been over three years since the world famous Kennedy Space Center (KSC) last felt the rumble of a launch from within its grounds. However, the spaceport hasn’t fallen completely silent, as a realignment of the center’s role continues apace, ahead of the new era of commercial and government launches that may ultimately result in humans…