Tag: STS-134
-

STS-133 rolls out to 39A – Managers call for ET-122 radius block installation
Discovery has completed her journey back out to Pad 39A with her modified External Tank (ET-137), with first motion at 8pm local on Monday evening, following an issue-free installation of radius blocks on most of its intertank stringers. With a high-level of confidence in the mitigation of further cracks on the stringers during loading and…
-

STS-134: Endeavour set for February 28 rollover – ET-122 borescope checks
Endeavour is set to depart from her Orbiter Processing Facility (OPF-2) on February 28, as milestones begin to align for her April 19 (No Earlier Than) launch to the International Space Station (ISS). With her External Tank (ET-122) and Solid Rocket Boosters (SRBs) mated, borescope inspections of ET-122’s stringers have been completed. STS-134 Latest: Endeavour’s…
-

STS-134 officially moved to April 19 – ET-122 stringers may be inspected
Endeavour’s final mission has slipped to the second half of April – as expected – due to the realignment of her older sister’s STS-133 mission to February 24. The April 19 mission, which remains under the command of Mark Kelly, has a large amount of contingency time in its flow, which will allow for inspections…
-

STS-134: Endeavour’s milestones realigned for April launch target
Pending the successful outcome of STS-133’s External Tank (ET-137) clearance for flight, managers have created a preliminary schedule for Endeavour’s realigned milestones. Currently, STS-134’s April 1 launch date is only a placeholder, but remains a target that can be achieved – providing Discovery doesn’t slip from her early February launch window. STS-134 Latest: Endeavour final…
-

STS-134: Endeavour’s slip to aid AMS change – New EVA protocol in work
NASA managers are realigning Endeavour’s processing flow milestones, as her launch date slips to an interim placeholder of April 1, 2011. Although the original late February launch date was fully supported by all the hardware elements participating in STS-134, the slip allows for extra contingency time for late changes to be carried out on the…
-

STS-134’s additional EVA to pick up on deferred ISS Stage work
The changes to Endeavour’s final mission have been outlined at a Program Requirements Control Board (PRCB) meeting, which approved the addition of two docked days and a fourth EVA for STS-134. The additional work will focus on the installation of the FGB Power Data Grapple Fixture (PDGF), which was deferred from ISS US EVA-15, due…
-

STS-134 mission to officially increase by two days and one EVA
Endeavour’s final mission will be officially extended next week, when mission managers approve a Change Request (CR) to add a fourth EVA and a subsequent increase of the mission duration by two days. Originally a 12+1 mission, Endeavour is being tasked with the delivery of the AMS-02 (Alpha Magnetic Spectrometer-02) to the International Space Station…
-

MAF speak of their pride in returning ET-122 to the Shuttle manifest
NASA and Lockheed Martin managers at the Michoud Assembly Facility (MAF) have spoken pride in the manufacturing, assembly, and repair work on External Tank 122 (ET-122), which was damaged by Hurricane Katrina five years ago. On Monday morning, the tank was rolled from Building 420 to the Pegasus barge that will carry it to Kennedy…
-

STS-134: Hardware and planning aligning for Endeavour’s final mission
Endeavour is deep into her processing flow for the STS-134 mission to the International Space Station (ISS), as engineers worked through a few hiccups with her AMS payload. Managers continue to work on the STS-134 mission baseline, which may include a fourth EVA. ET-122 is also now assigned to STS-134 in processing charts – pending…
-

Managers delay STS-134 ET/SRB mate ahead of tank allocation options
With STS-135 heading into mission planning for a June 28, 2011 flight – pending the required funding being passed by lawmakers – managers have opted to delay the mating of STS-134’s External Tank (ET) and Solid Rocket Boosters (SRBs) to December, in order to allow a potential tank swap between ET-138 and ET-122. Meanwhile, a…